Pillar: Planning and buildings

Can a masía on non-developable land in Catalonia be restored or given a new use?

Licences and legality·13 min read·Updated 12 November 2026
On this page

In Catalonia, yes, if the municipal plan lists it in its catalogue of masías and rural houses: a masía (traditional farmhouse) can then be restored as a home, for rural tourism or for another use in article 47.3 bis of the Catalan Planning Act that the plan allows, under a town hall licence, with a report from the territorial planning commission in the article 50.3 cases. Where no catalogue exists yet, the project needs the town hall's prior approval and that commission's final approval (transitional provision fifteen).

Map from the sample report: Shape and measurements. The plot measures 997 m² with 8 simplified sides; the longest, H–I, is 25.3 m.Map legend: Shape and measurements
This example comes from Torrox in Andalusia, not from Catalonia: the page shows how the report measures the shape and dimensions of a plot, without applying the Catalan Planning Act or any catalogue of masías. Page 11 of 116 of the TerrenoCheck sample report, a real plot (6633007BC5963S, Xàbia/Jávea (Alicante)): Shape and measurements. The plot measures 997 m² with 8 simplified sides; the longest, H–I, is 25.3 m. Layer source: Dirección General del Catastro. Aerial image: © Instituto Geográfico Nacional (PNOA), CC BY 4.0. See the report page

A masía outside the built-up area usually stands on what Catalan plans call 'sòl no urbanitzable', non-developable land. The Catalan Planning Act (TRLUC, Decreto Legislativo 1/2010; BOE consolidated text, last update published on 3.7.2026) bans plot subdivision for development there (art. 47.2) and gives masías a regime of their own. The rules common to all of Spain are in what you can do on rustic land.

What the catalogue of masías and rural houses is

The general plan or a special plan must identify, in a specific catalogue, the buildings on non-developable land that may be rebuilt or restored, and explain why they deserve to be kept (art. 50.2). In Catalan papers it is the 'catàleg' of 'masies i cases rurals'. Article 47.3 covers four groups.

Building (art. 47.3)Extra volumeDivision into units
a) Rebuilding and restoring masías and rural houses (architectural, historical, environmental, landscape or social reasons)Yes, on conditions (50 bis.1)If the plan allows it (50 bis.4)
b) Rebuilding and restoring other buildings older than the municipality's first general plan (architectural or historical reasons)Yes, on conditions (50 bis.1)If the plan allows it (50 bis.4)
c) Restoring disused rural buildings, to correct their negative environmental or landscape impactNo; it may be reduced (50 bis.3)Not provided for
d) Rebuilding and restoring farm and forestry buildings from 1956 or earlierNo (50 bis.1)Not provided for

'Not provided for': article 50 bis.4 allows it only for groups a and b. Source: TRLUC, arts. 47.3 and 50 bis. Accessed 12 November 2026.

Residential use is listed for 'masías o casas rurales' (art. 47.3 bis.a): that letter does not cover turning a group b barn into a house.

How to find out whether the masía is catalogued

Anyone may request the certificate (art. 105.1), so your lawyer can do it while you are abroad; your own paperwork is in the NIE for foreign buyers.

Town hall. Ask for the building's catalogue entry and for a 'certificat de règim urbanístic' (planning status certificate). The town hall must notify it within one month of the application reaching its general register, and the certificate is valid for six months (art. 105.2 and 105.3). More in the planning certificate.

Catalan planning register. The 'Registro urbanístico de Cataluña' guarantees in-person and online consultation of the plans in force (art. 103.2). Its portal is still named 'RPUC - Registre de planejament urbanístic de Catalunya': search for the municipality's general plan and, if there is one, the special plan containing the catalogue.

Mapa urbanístic de Catalunya (MUC). The Generalitat's viewer merges the land classification and zoning of the general plans. It has 'valor informatiu' (information value only), and none of the layers of its WMS service (classification, zoning, sectors) is the catalogue.

A real example: the MUC at l'Esquirol

The MUC at l'Esquirol (Osona)Orthophoto under the zoning layer of the Mapa urbanístic de Catalunya; the point queried, in the centre, is ordinary non-developable land (N1).The MUC at l'Esquirol (Osona)N1MUC zoning (layer MUC_4QUAL)N1 'No urbanitzable, Ordinari'N2 'No urbanitzable, Protecció local'Point queried: non-developable land, N1The map does not say if a masía is listed.
A real reading taken on 12.11.2026 at l'Esquirol (Osona), point X 445,000, Y 4,650,000 (ETRS89 UTM 31N). The MUC WMS service answers 'Sòl no urbanitzable' on layer MUC_2CLAS and 'N1, No urbanitzable, Ordinari' on layer MUC_4QUAL, with the municipal code 'F, Protecció Forestal'. Sources: Generalitat de Catalunya, MUC WMS service; ICGC, current orthophoto; ICGC, administrative divisions. Accessed 12 November 2026.

The map shows the land class and the plan's zoning code, not the catalogue.

How much non-developable land there is

Non-developable land by regionHectares, MUC at 1.1.2023 (AMB: 1.7.2022) Alt Pirineu i Aran: 573,295 ha; Ponent: 543,218 ha; Comarques gironines: 525,883 ha; Comarques centrals: 490,703 ha; Terres de l'Ebre: 321,331 ha; Camp de Tarragona: 249,481 ha; Metropolità de Barcelona: 162,173 ha; Penedès: 154,445 haNon-developable land by regionHectares, MUC at 1.1.2023 (AMB: 1.7.2022)Alt Pirineu i Aran573,295 haPonent543,218 haComarques gironines525,883 haComarques centrals490,703 haTerres de l'Ebre321,331 haCamp de Tarragona249,481 haMetropolità de Barcelona162,173 haPenedès154,445 ha
Non-developable land by planning region, in hectares. MUC data at 1.1.2023 (Barcelona metropolitan area at 1.7.2022). Source: Generalitat de Catalunya, MUC, Dades bàsiques de Catalunya (June 2024). Accessed 12 November 2026.

The MUC counts 3,020,529.97 hectares of non-developable land out of 3,210,867.11 in total, or 94 %.

Which uses the law allows

Catalogued buildings may be reused, 'de acuerdo con el correspondiente plan urbanístico' (in line with the relevant plan), for ten uses (art. 47.3 bis):

  • a home, in the case of masías or rural houses;
  • a home with tourist-use business, in masías or rural houses;
  • a hotel, excluding aparthotels;
  • rural tourism;
  • leisure-time education;
  • artistic creation or craft production;
  • practice of the liberal professions;
  • a restaurant;
  • public facilities;
  • community or corporate services.

Other uses are possible if the estate has an approved forestry or estate management plan and shows that it is being carried out (art. 47.3 ter). The catalogue entry gives the uses the plan allows for that house; all must be compatible with the farming carried on in the immediate surroundings (art. 47.3 quáter).

A 'vivienda de uso turístico' (holiday-let home) is compatible with a lawfully established family-home use (art. 47.8 bis); for the tourism permit, see holiday rental rules.

Which works are possible

Works must respect the original volume and massing; the conditions for replacing part of the building or adding volume are in rebuilding a ruin on rustic land. Three more rules:

  • Separate block. A block separate from the original may only serve uses ancillary to the main one, unless the main use is rural tourism or a hotel (art. 50 bis.2).
  • Original features. In a masía catalogued for environmental, landscape or social reasons, alterations justified in the project are allowed; if it was catalogued for architectural or historical reasons, only the minimum essential for a permitted use (art. 50 bis.5).
  • Division into units. 'División horizontal' (separately owned units) only for groups a and b, if the plan allows it and on the conditions of article 50 bis.4; never in the parts used as a hotel. Setting it up needs a planning licence (art. 187.1.k, with the exceptions of art. 187 ter).

Who decides, and how long it takes

Masía: which procedure appliesA Masía or rural house, catalogued: Municipal licence, with a territorial commission report only in the art. 50.3 cases.; B The municipality has no catalogue: Prior approval by the town hall, final approval by the territorial commission (DT 15, art. 48).; C A catalogue exists, house not in it: Art. 47.3 requires an entry (47.3 bis). What remains: a rural municipality's inventory (57 quater).; D A newly built home: Only a family home tied to a working rural holding (arts. 47.6.b, 49).Masía: which procedure appliesAMasía or rural house, cataloguedMunicipal licence, with a territorialcommission report only in the art. 50.3cases.BThe municipality has no cataloguePrior approval by the town hall, finalapproval by the territorial commission (DT15, art. 48).CA catalogue exists, house not in itArt. 47.3 requires an entry (47.3 bis). Whatremains: a rural municipality's inventory(57 quater).DA newly built homeOnly a family home tied to a working ruralholding (arts. 47.6.b, 49).
The procedure depends on whether the catalogue lists the house. Source: TRLUC, arts. 47, 48, 49, 50 and 57 quater and transitional provision fifteen. Accessed 12 November 2026.
StepWhoTime limitRule
Works licence for a catalogued masíaTown hallThe one set by local-government legislationTRLUC, arts. 50.1 and 188.2
Report on the effect on farmingThe department responsible for agriculture and livestockOne month at most; if it does not arrive, the file moves onTRLUC, art. 50.1; Decree 64/2014, art. 61
Report in the art. 50.3 casesTerritorial planning commission ('comissió territorial d'urbanisme')Two months at mostTRLUC, art. 50.3; Decree 64/2014, art. 60.1
Project in a municipality with no catalogueTown hall (prior approval) and territorial commission (final approval)One month of public consultation; the commission decides within three months of receiving the complete fileTRLUC, DT 15 and art. 48.2; Decree 64/2014, art. 51

Time limits of Decree 64/2014 from its consolidated text in the BOE, last amended on 6.5.2026; the mandatory-report cases are those of the Act now in force. Sources: TRLUC, arts. 48, 50 and 188; Decree 64/2014, arts. 51, 60 and 61 (consolidated text). Accessed 12 November 2026.

The two article 50.3 cases are the article 47.3 ter uses that the plan does not expressly allow, and works of partial replacement or extra volume, without a separate block, that the plan does not set out in enough detail. The farming report is requested if the project may disturb holdings in the immediate surroundings, and is not mandatory if the works only conserve, adapt or improve the building and keep the existing permitted use (art. 50.1).

Do not rely on the town hall's silence: article 188.2 excludes from deemed approval, among other acts, new-build works on non-developable land and anything that breaches planning law.

If there is no catalogue, or the house is not in it

Until the general plan or a publicly promoted special plan contains the catalogue, rebuilding or restoration may be authorised through the article 48 procedure, for any of the permitted uses, hotel included, by justifying the reasons for recovering the building (DT 15, paragraph 1).

If the municipality has a catalogue and the house is not in it, article 47.3 does not cover it. Since 7.5.2026 rural municipalities may also approve an inventory of buildings with nothing to preserve, with the uses, the maximum extension and the municipal licence of article 57 quater.

A new house on the estate

As a newly built home, the Act allows only a family home 'directa y justificadamente' (directly and justifiably) tied to a farming, livestock, forestry, natural-resource or, in general, rural holding (art. 47.6.b), under the article 48 procedure (art. 49.1.b). Article 47.6 bis sets the four circumstances in which that tie is presumed.

Unlicensed works: which time limits run

Six years, or never Action to restore the physical state of the land lapses six years after the breach occurred or, where applicable, after the unlawful works ended or the unlawful activity ceased. If an unlawful administrative permit covers the works, the six years run from its declaration as void or voidable. Restoration orders already issued lapse after six years (art. 207.1 and 207.2). None of this applies on land the plan assigns to public open space or roads, nor on land it classifies or must classify as non-developable under article 32.a (among other factors, sectoral or territorial protection, master plans and protection of public property): there the action and the order never lapse (art. 207.3).

Infringements lapse after six years if very serious, four if serious and two if minor, from the day they are committed or, if the conduct continues or is prolonged, from when it ends or ceases; on that same land they do not lapse (art. 227). Ask in the certificate whether the estate is non-developable land under article 32.a or 32.b: the MUC does not settle it. The general case is in illegal house on rustic land.

What you pay

The purchase tax (ITP), with the Catalan rates, is in the cost of buying a property. The works are charged ICIO, a municipal construction tax set by each town hall at no more than 4 % of the 'coste de ejecución material': the cost of the construction itself, excluding VAT, fees and the builder's profit (TRLRHL, art. 102). The licence may also carry a municipal fee (art. 20.4.h).

Hypothetical example

ICIO on a restoration

On a restoration with a 'coste de ejecución material' of €300,000, ICIO is €12,000 at the maximum 4 % rate, or €9,000 at a municipal rate of 3 %.

What to do, in order

  1. Ask the town hall for the catalogue entry and the planning status certificate. One month from the application; fee per the municipal tax by-law.
  2. Read the plan and the catalogue on the Catalan planning register's portal: online consultation (art. 103.2).
  3. Locate the estate in the MUC viewer by municipality, address, cadastral reference or UTM coordinates: classification and zoning, for information only.
  4. Order a 'nota simple' (land registry extract): registered built area and charges. See how to order one.
  5. With an architect, compare the entry with your project and ask whether it will need a report from the territorial commission (up to two months) or from agriculture (up to one month).
  6. Sign a deposit contract conditional on the licence or report still missing: the arras contract.
Before you pay a deposit
  • You hold the catalogue entry, with the reasons for cataloguing and the permitted uses.
  • The use you want is in the entry and in article 47.3 bis, or the estate has the management plan of article 47.3 ter.
  • You know whether the works add volume and need the territorial commission's report.
  • Every annexe, porch or pool has a licence, or you know when it was finished and whether the land falls under article 32.a.

Once you have chosen an estate, order the report by its cadastral reference and bring its measurements and maps to the town hall.

This guide is general information on the rules in force on the date each source was checked. It is not legal advice: for a specific purchase, ask a lawyer or the notary. Written and reviewed by the TerrenoCheck team (Kandyb Studio, Paweł Kandybowicz, responsible for the content). If you find a mistake, write to us and we will correct it.

Common questions

Can I turn a masía into a rural tourism business?

Yes, if it is in the catalogue and the plan allows that use: rural tourism is on the article 47.3 bis list and must be compatible with the farming carried on in the immediate surroundings (art. 47.3 quáter). New buildings to extend a rural tourism or hotel use require a special planning instrument ('plan especial urbanístico') to be processed first (art. 47.6.g).

Can a masía be split into several homes?

Only if the plan allows it and on three conditions: the original character is not altered, the main historical elements are respected and habitability rules are met (art. 50 bis.4). The parts used as a hotel cannot be divided into units or held under any other form of co-ownership.

What if the masía is not in the catalogue?

It depends on the municipality. If its plan has no catalogue yet, the project can be authorised through the article 48 procedure, with final approval by the territorial planning commission (DT 15). If there is a catalogue and the house is not in it, article 47.3 does not apply. In a rural municipality it may be in the article 57 quater inventory, approved by the full council after at least one month of public consultation and a report from the territorial commission: with a municipal licence it allows permanent main residence, if the building forms part of an inhabited group, and four other uses, with an extension up to a maximum resulting built area of 150 m² if the need is justified and the fit with the landscape is shown.

Can I build a new house on the masía's land?

As a home, only a family home directly and justifiably tied to a working rural holding (art. 47.6.b). Article 47.6 bis presumes that tie when four circumstances concur: a rural municipality of fewer than five thousand inhabitants; a developer who is a descendant of the holder of a family rural holding in the municipality, the holder living on it; a developer who works on the holding or earns income from it; and a presumption not used before for the same holding. A buyer with no farm in the family does not fit that presumption. A separate block created by extending the masía may only serve uses ancillary to the main one, unless that use is rural tourism or a hotel (art. 50 bis.2).

Does an extension built without a licence become time-barred?

Under article 207, action to restore the land lapses six years after the breach occurred or, where applicable, after the unlawful works ended; where an unlawful administrative permit covers them, six years after it is declared void or voidable. It never lapses on non-developable land under article 32.a, or on public open space and roads.